You may choose to migrate all of your data into a CockroachDB cluster at once. However, for larger data stores it's recommended that you migrate data in separate phases. This can help break the migration down into manageable slices, and it can help limit the effects of migration difficulties.

This page explains when to choose each approach, how to define phases, and how to use MOLT tools effectively in either context.

In general:

  • Choose to migrate your data all at once if your data volume is modest, if you want to minimize migration complexity, or if you don't mind taking on a greater risk of something going wrong.

  • Choose a phased migration if your data volume is large, especially if you can naturally partition workload by tenant, service/domain, table/shard, geography, or time. A phased migration helps to reduce risk by limiting the workloads that would be adversely affected by a migration failure. It also helps to limit the downtime per phase, and allows the application to continue serving unaffected subsets of the data during the migration of a phase.

How to divide migrations into phases

Here are some common ways to divide migrations:

  • Per-tenant: Multi-tenant apps route traffic and data per customer/tenant. Migrate a small cohort first (canary), then progressively larger cohorts. This aligns with access controls and isolates blast radius.

  • Per-service/domain: In microservice architectures, migrate data owned by a service or domain (e.g., billing, catalog) and route only that service to CockroachDB while others continue on the source. Requires clear data ownership and integration contracts.

  • Per-table or shard: Start with non-critical tables, large-but-isolated tables, or shard ranges. For monolith schemas, you can still phase by tables with few foreign-key dependencies and clear read/write paths.

  • Per-region/market: If traffic is regionally segmented, migrate one region/market at a time and validate latency, capacity, and routing rules before expanding.

Tips for picking slices:

  • Prefer slices with clear routing keys (tenant_id, region_id) to simplify cutover and verification.

  • Start with lower-impact slices to exercise the migration process before migrating high-value cohorts.

Tradeoffs

All at once Phased
Downtime A single downtime window, but it affects the whole database Multiple short windows, each with limited impact
Risk Higher blast radius if issues surface post-cutover Lower blast radius, issues confined to a slice
Complexity Simpler orchestration, enables a single cutover More orchestration, repeated verify and cutover steps
Validation One-time, system-wide Iterative per slice; faster feedback loops
Timeline Shorter migration time Longer calendar time but safer path
Best for Small/medium datasets, simple integrations Larger datasets, data with natural partitions or multiple tenants, risk-averse migrations

MOLT toolkit support

Phased and unphased migrations are both supported natively by MOLT.

By default, MOLT Fetch moves all data from the source database to CockroachDB. However, you can use the --schema-filter, --table-filter, and --filter-path flags to selective migrate data from the source to the target. Learn more about schema and table selection and selective data movement, both of which can enable a phased migration.

Similarly, you can use MOLT Verify's --schema-filter and --table-filter flags to run validation checks on subsets of the data in your source and target databases. In a phased migration, you will likely want to verify data at the end of each migration phase, rather than at the end of the entire migration.

MOLT Replicator replicates full tables by default. If you choose to combine phased migration with continuous replication, you will either need to select phases that include whole tables, or else use userscripts to select rows to replicate.